Project-Controlling
Project-Controlling collects information about the current project situation and compares to the baseline of the project (scope, schedule, cost, resources, quality and risks). Corrective actions may be taken in case of variances or requested scope changes. It follows the usual Plan-Do-Check-Act cycle by W.E. Deming. Wikipedia: PDCAPlanDoCheckAct-Cycle |
Step within the process:
Controlling steps according to IPMAPreparation: | What issues are going to be checked? What papers are needed? Is a short status at beginning necessary? Is the risk plan up to date? |
Doing: | Actual meeting according agenda with objectives |
Updating plans: | Updating project handbook and relevant documents |
Communication: | Informing stakeholders actively about the project progress and issues |
Closing: | Archiving status report and documents |
Output:
Updated plans (schedule, cost, WBS, Work packages etc.)
Status report
Example Status-Report
Example: Status-Report |